Following our appointment we undertake to:

  • Serve an Initial Notice onto the Local Authority.
  • Liaise as necessary with design consultants to ensure compliance with the Building Regulations.
  • Consult with the local fire authority (where required) on the proposed fire safety strategy and notify them of any significant departures from the design.
  • Retain full records of the design assessment philosophy for future reference and continuity of control.
  • Assess main design proposals and provide our compliance report detailing any non-compliance items to the designated persons.
  • Assess amendments throughout the scheme and provide written feedback on compliance and non-compliance to the designated persons.
  • Consult with sewerage undertakers and other similar bodies where required to ensure the design satisfies their requirements, and notify such bodies of any significant departures from the design.
  • Provide advice on local acts where relevant to Building Regulations.
  • Provide on request our complaints procedure.

Following commencement of site works we undertake to:

  • Liaise with the contractor/designated persons to understand the build programme and to set out an inspection plan.
  • Carry out unannounced and announced site inspections in accordance with the inspection plan, with no less than one visit per month for a live project.
  • Identify non-compliance work promptly to the responsible persons and indicate measures believed necessary to remedy contraventions.
  • Issue a final certificate to the Local Authority, Fire Service (when required) and designated persons once we are satisfied the scheme meets compliance with the building regulations.